Free PMP® Exam Sample Question

Which is the process of creating, collecting, distributing, storing, and disposing of performance information, including status reports, progress measurements, and forecasts?

A.) Manage Communications

B.) Control Communications

C.) Manage Stakeholder Engagement

D.) Plan Communications Management

Question provided by The PM Exam Simulator: www.pm-exam-simulator.com

Answer & Explanation

Correct Answer: A)

Manage Communications is the process of creating, collecting, distributing, storing, retrieving, and disposition of project information including status reports, progress measurements, and forecasts.

Question provided by The PM Exam Simulator: www.pm-exam-simulator.com

Reference: PMBOK Guide 5th Edition, page 297

Disclaimer and Copyright Statement

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.