December 01 2018 at 12:00AM
Free PMP® Exam Sample Question for December
The Perform Quality Assurance process on a project could create the requirement to update which of the following documents?
A.) Quality Management Plan
B.) Project Charter
C.) Scope Statement
D.) Enterprise Environmental Factors
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: A)
After the Quality Audit you may have to create some change requests. The Quality Management Plan might get changed if the change requests are approved. You cannot change the Project Charter, Enterprise Environmental Factors, or Scope Statement.
Reference: PMBOK Guide 5th Edition, page 248
Disclaimer and Copyright Statement
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.